Calculation on the Direct Commissioning Crafts of the Oil Pipeline
Xu Chenchen, Fu Xuan, Fu Guoqing, Fu Xudong, Chai Yanqiang, Xu Yongfeng
In order to ensure pipeline commissioning safety and avoid security risks because of the direct contact between the air and oil, a progress of water isolation was necessary. And how to determine the amount of optimal isolation medium is becoming a new subject. The factors affecting the isolation medium quantity from the point of commissioning process was analyzed and a model to calculate the amount of isolation medium and the mixed oil quantity in a long slope pipeline was built while commissioning, based on existing empirical models, combined with field data. The relative error was in the acceptable range.
|
|